Ikeja Electric (IE) has apologised to customers in parts of Lagos after five Band A electricity feeders failed to meet the minimum daily power supply requirement of 20 hours on September 30 and October 1, 2026.
The electricity distribution company disclosed the shortfall in a public notice published on Friday, October 2, explaining that the affected feeders experienced varying levels of electricity supply disruption.
Read also
Workers declare 3-day warning strike as details emerge
According to the notice, the affected feeders serve communities in Oshodi and Shomolu, with the outages linked to faults on Ikeja Electric's 11-kilovolt (11KV) and 33KV distribution lines, as well as instability on the national grid managed by the Transmission Company of Nigeria (TCN).
PAY ATTENTION: From breaking news to viral moments. Follow Legit.ng on Instagram!
The company apologised to affected customers, saying it regretted the inconvenience caused by its inability to meet the guaranteed service level.
In its statement, Ikeja Electric said:
The 33-IsoloTCN-AIRPORT feeder in Oshodi recorded the most significant disruption, receiving no electricity supply on September 30 and only 4.52 hours on October 1.
Ikeja Electric attributed the shortfall on the feeder to a fault on its 33KV line.
Read also
41 million businesses, 6% trade exports: Why LTIF 2026 is taking the trade conversation to Accra
Another affected feeder in Oshodi, the 33-IsoloTCN-AJAO line, supplied electricity for 16.73 hours on September 30 and 18.17 hours the following day.
The company attributed the disruptions to a combination of maintenance-related issues on its lines and instability from the national grid.
Two other feeders in Oshodi also fell short of the required service level on both days.
The 11-Lagos HomsINJ-T1-Estate and 33-EjigboTCN-IGANDO feeders each recorded 18.57 hours of electricity supply on September 30, before their supply hours dropped to 16.20 on October 1.
Ikeja Electric identified faults on its 33KV infrastructure as the cause of the disruptions affecting the two feeders.
In Shomolu, the 11-Ilupeju BypassINJ-T1-Obanikoro feeder received 15.90 hours of electricity on September 30 and 18.50 hours on October 1.
The company attributed the shortfall to issues involving both its distribution network and the transmission grid.
Band A customers in Nigeria pay a higher electricity tariff in exchange for a minimum of 20 hours of daily supply. When that threshold is not met, providers like Ikeja Electric are expected to compensate affected customers.
Read also
Power blackout hit 2 Nigerian states, TCN gives reason
Legit.ng previously reported that Ikeja Electric opened a compensation portal for Band A customers to receive free units following service failures, and that the company had since credited electricity units to affected customers in response to earlier supply shortfalls.
Meanwhile, Legit.ng earlier reported that an Ikeja Electric worker suffered an electric shock while carrying out repairs on a utility pole at Gbagada Bus Stop in Lagos.
The worker, an IKEDC field technician, was reportedly carrying out repairs on the pole when the incident occurred on Thursday, September 3, 2026.
A viral video showed two IKEDC colleagues struggling to bring the victim safely down from the elevated ladder where he was stuck.

Source: Legit.ng
Victor Enengedi (Business HOD) Victor Enengedi is a trained journalist with over a decade of experience in both print and online media platforms. He holds a degree in History and Diplomatic Studies from Olabisi Onabanjo University, Ogun State. An AFP-certified journalist, he functions as the Head of the Business Desk at Legit. He has also worked as Head of Editorial Operations at Nairametrics. He can be reached via victor.enengedi@corp.legit.ng and +2348063274521.

source

Leave a Reply

Your email address will not be published. Required fields are marked *